HomeAsian ContentsTender GalleryBuy Sell GalleryTradeHub GalleryServicesBuzzChatShowrooms

Israel Contents

Contents

General Section

General Information

Infrastructure

Introduction

Railways

Roads

Ports

Telecom

Energy

Power

Oil & Gas

Banking

Banking

Travel

Travel

Policies

Finance Policy

Trade

Trade

Exim

Tax Structure

Tax System

Important Contacts

Important Contacts

   
 

 

 
   

 

 

Energy Power(Electric)

 Other Link : Energy

Israel Electric Corporation & its expansion plans 2010

The Electricity Commissioner is responsible to the Minister to supervise, approve and plan for the current and future needs of the State and its citizens so that demand will always be able to be met, He is also responsible for implementing the Minister's policies in the field of electric power.  

The Israeli Electric Power System and its Expansion Plans 2010

The Israel Electric Corporation (IEC) incorporated in 1923 is a Public Utility, generating and supplying electricity throughout the State of Israel. The IEC directly serves a population of about 5.5 million in an area of approximately 21,500 sq.km For the time being, the IEC also provides electricity to Judea, Samaria and the Gaza Strip with a total population of ca 1.7 million. The electric system is isolated from neighboring systems and had a peak load of 6,000 MW in January 1996 with a total installed capacity of 7700 MW as of today. Coal fired unites comprise about 550% of the system's installed capacity, while the share of oil fired units and gas turbines (using diesel oil) is 29% and 21% respectively.

The main transmission voltage is 161 kV, while the first stage of a 400 kV transmission voltage grid has been operational since 1990 and is planned to be superimposed on the 161 kV network as the main transmission grid.

The Israeli system has expanded over the last ten years at the rate of 8.8% per annum - resulting in the extensive projects and equipment purchases - exceeding those of much larger systems.

The IEC is entering a new era under license which has replaced the monopoly and is open to tenders and limited IPP production, with a newly formed Public Utility Commission. IEC is now introducing Independent Business Centers which will make supervision easier and more efficient as well as heighten competitiveness.

The Generation Expansion Plan until 2010

Year

Gross electricity generation (Gwh) 

Peak demand (MW)

Additional generation units (MW) 

Type*

1999

36,239

7,545

1X75;2X(150:180);200

OS;IGT;IPP 

2000

37,985

7,911

2X100;1X150;1X550

UB&ST;OS;IPP;CFU 

2001

39,596

8,285 

11X550

CFU

2002

41,167

8,626 

1X30

OS;IPP

2003

42,571

8,930 

1X150

OS;IPP

2004

43,9902

9,204 

1X150

OS;IPP

2005

45,078

9,493 

1X350;1X100

CC;IPP

2006

46,735

9,844 

2X120

IGT

2007

48,422

10,220 

1X120;1X350

IGT;CC

2008

50,161

10,560 

1X120;1X350

IGT;CC

2009

51,949

10,968 

3X117;1X350

CAIR;CC

2010

53,719

11,368 

1X350

CC

IGT: industrial type gas turbine
CFU: coal fired unit
CC: combined cycle
UB&ST: additional unfired boiler & steam turbine to existing IGT
OS: oil shale unit
CAIR: compressed air plant based on salt caverns close to the Dead Sea
IPP: independent power producer
N.B. The proposals ibid may change on the basis of fuel basket prices and strategic considerations.

The Transmission Expansion Plan (1995 - 2010)

In the period of 1996 - 2010 the IEC 400 kV system will be extended from 346 km (circuit length) to 1'900 km. Twelve 400/161 kV major substations will be installed at Gan-Sorek (9.97), Zvulun (7.98), Ramat-Hovav (10.98), Lavi, Yavor, Rotem Plane, Ganot, North Tel-Aviv, Even-Sapir, Adumim Plane, Gazer and Tirat Carmel adding 12'500 MVA of 400q161 kV tie transformer capacity to the system. The development plan includes an additional 1,640 kms of 161 kV circuits, installation of 72 hv/mv substations and an increase of transformer capacity to the system. The development plan includes an additional 1,640 kms of 161 kV circuits, installation of 72 hv/mv substations and an increase of transformer capacity from 7,869 MVA to 17,400 MVA by the end of 2005.

Procurement
IEC purchases boilers, turbogenerators, preceptors, FGD equipment, auxiliary equipment, etc., for its power stations and switchgear, transfiormers and other relevant equipment for its substations through competitive tenders, from well-known and experienced manufacturers. Part of the equipment Is purchased from local Israeli manufactures.

Several important and interesting electricity projects have been proposed since the start of the Peace Process - the most challenging being the interconnection of the electricity grids of all the countries in the region.

 

 

About Us | Advertise With Us | New Visitors | Benefits | Buy/Sell Guide | Bidding Guidelines | Members Login

  ©2000- Matrix net-on-line Limited All Rights Reserved /Disclaimer